Skip to content

OperatingItaly · Lombardia

Lonato 1

  • Solar carport
  • Charging infrastructure

Capacity

6.04 MWp

Luftaufnahme des Solarcarports Lonato 1 über einem Fahrzeug-Logistikplatz, dahinter Lonato del Garda

6.04 MWp solar carport for ARS Altmann AG in Lonato del Garda, operating since January 2026. The plant covers a large vehicle logistics yard and supplies 30 charging points at 22 kW and 9 at 50 kW. The second phase, Lonato 2, is in development.

  • 158 string inverters
  • Around 310 km of power cable
  • Most of the power is consumed on site

Milestones

Project progress100%
  1. Test drilling

    Apr 2024 · completed

  2. Construction start

    Oct 2024 · completed

  3. Commissioning

    Jan 2026 · completed

Key facts

Location
Lombardia, Italy
Capacity
6.04 MWp
Commissioning
Jan 2026
Enquire about this project

News on this project

Other projects

  • Technology: Battery storage

    Ostiglia BESS

    Permitted

    Lombardia, Italy

    View project
    Storage power
    80MW
    Commissioning
    2028
  • Technology: Solar carport

    Lombardia, Italy

    View project
    Capacity
    17MWp
    Commissioning
    2009
  • Technology: Solar carport

    Ceneselli

    Operating

    Veneto, Italy

    View project
    Capacity
    13MWp
    Commissioning
    2013

Banks and financing partners