Under constructionGermany · Mecklenburg-Vorpommern
Kargow I + II
- Ground-mounted
Capacity
40.8 MWp
Two ground-mounted plants totalling 40.8 MWp near Waren (Müritz). Kargow complements the Schlön cluster and feeds in via the same Federow substation.
- Shares the substation with Schlön
Milestones
Project progress35%
Permit
2025 · completed
Construction start
Oct 2025 · completed
Commissioning
Q2 2027 · planned
Key facts
- Location
- Mecklenburg-Vorpommern, Germany
- Capacity
- 40.8 MWp
- Commissioning
- Q2 2027 (expected)
Business units involved
Other projects

Technology: Ground-mounted + Battery storage + Substation
View projectSchlön
OperatingMecklenburg-Vorpommern, Germany
- Capacity
- 60.81MWp
- Commissioning
- 2026

Technology: Ground-mounted + Battery storage + Substation
View projectBergholz
OperatingMecklenburg-Vorpommern, Germany
- Capacity
- 57.82MWp
- Commissioning
- 2026

Technology: Ground-mounted + Battery storage + Substation
View projectRockensußra
Under constructionThüringen, Germany
- Capacity
- 84MWp
- Commissioning
- 2027